Project Name: Construction Investment Project of the Ha Dong – Xuan Mai Road (Connecting Route between Binh Minh and Chuong My).
Location: Binh Minh Commune, Yen Nghia and Chuong My Ward.
Investment Objective: To construct the road in a synchronized manner, contributing to overall socio-economic development.
Proposed Scale: L = 25 km; B = 60 m; section lengths by localities include: Phu Luong 1,975 m; Binh Minh 2,125 m; Yen Nghia 1,870 m; Chuong My 5,880 m; Phu Nghia 4,450 m; Tran Phu and Xuan Mai 8,700 m.
Proposed Implementation Schedule: 2025–2030.
Preliminary Total Investment: 10,000 billion VND.
Investment Form: PPP.
Investor Selection Method: Open bidding.
Project Proposal Lead: Investor.